Software Project Management Unit 3 Notes AKTU (BOE068)

AKTU · BTECH · Semester 6 · Software Project Management · Unit 3 · Notes

AKTU Software Project Management (BOE068) Unit 3 notes for B.Tech Semester 6 – Activity Planning and Risk Management. Topics: Activity Planning and…

A preview is available. Sign in or check access options in the reader for the complete resource.

Unit 3: Activity Planning and Risk Management – AKTU syllabus topics

  • Activity Planning and Scheduling: Sequencing and Scheduling, Network Planning Models
  • Critical Path Method: Forward and Backward Pass, Float and Critical Path
  • PERT Technique: Monte Carlo Simulation
  • Risk Management: Risk Identification and Assessment, Risk Planning and Mitigation
  • Resource Allocation: Cost Schedules

Most asked AKTU PYQ questions from Unit 3

  1. Q1f. Discuss the structure of the activity node in the activity network. (2 marks, 2023-24)
  2. Q1f. Discuss the structure of activity node in activity network. (2 marks, 2022-23)
  3. Q2c. Illustrate project scheduling with the help of various project schedule activities. (10 marks, 2023-24)
  4. Q5b. Consider the following project specifications with estimated activity durations and precedence requirements: | Activity | Activity Description | Durations (weeks) | Precedents | | --- | --- | --- | --- | | A | Hardware selection | 8 | | | B | System configuration | 5 | | | C | Install hardware | 3… (10 marks, 2023-24)
  5. Q5a. In the application of risk management to software development projects has been strongly advocated. In practice, however, managers are often reluctant to apply the techniques. Derive the reasons you might think for this. (10 marks, 2023-24)
  6. Q2c. Illustrate Work Breakdown Structure (WBS) in context to software project and product. (10 marks, 2022-23)
  7. Q5b. Design an activity network diagram by taking a suitable example using PERT Technique. Find project schedule time and Critical path. (10 marks, 2022-23)
  8. Q5a. Formulate following Using CPM (i) Construct the project network. (ii) Perform Project Time estimation using forward and backward pass (iii) Identify the critical path. The table contains the activity label, its respective duration (in weeks) and its precedents. | Activity | Duration (in weeks) |… (10 marks, 2022-23)
  9. Q4b. Discuss about the Forward Pass and Backward Pass techniques in Activity Planning and Risk Management. (10 marks, 2021-22)
  10. Q2c. What do you mean by Project schedules? Mention the Objectives of Activity planning. (10 marks, 2021-22)

AKTU paper codes: BOE068, KOE068

Other Software Project Management units

Software Project Management previous year papers

More Software Project Management resources

More versions of this resource

Browse all notes · Semester 6 notes · Software Project Management notes